What we do
From a single kitchen to a multi-dwelling development, every estimate is prepared with the same structure, the same price library and the same attention to existing conditions.

01

02

03

04

05
…extremely impressed with the detail and accuracy.Alexander Knight · Google review
Send us a rough sketch. We turn it into a scaled plan, price it line by line, and hand it back as a proposal in your branding, ready for your client.
The price library
Our price library goes well beyond a standard standalone database. It holds material costs to the smallest component, from M12 bolts and timber frame screws for every element of construction to Colorbond cladding, concrete and the majority of general construction materials.
Alongside it sits a labour database developed over eight years of estimating. Together they have come to define our company.
8 years
labour database development
3,400+
construction recipe options
1,500+
priced supply and labour cost codes
28
trade and cost categories
| Item | Unit | Supply | Labour |
|---|---|---|---|
| M16 × 105 mm anchor bolt | each | $8.80 | $5.50 |
| SDS structural screw | each | $1.20 | $0.45 |
| Yellow tongue flooring screw | each | $0.15 | $0.30 |
| 90 × 45 mm timber roof batten | lm | $3.20 | $4.10 |
| Colorbond roof flashing | lm | $18.20 | $27.10 |
| Footing reinforcement, external | m | $14.00 | $18.20 |
| Concrete, external footings | m³ | $192.50 | $99.79 |
| Colorbond fencing, supply and install | lm | $103.50 | |
| 2.8 m screw pile, supply and install | each | $797.40 |
Figures: Renovation Estimating price library, pricing level 1, ex GST. Every item also carries rates for pricing levels 2 to 8.
The estimating experience
Every estimate is built from measured quantities and coded cost items, organised the way a project is built. Each item carries its quantity, unit, rate and selected specification level, so every total can be traced back to its source.
How an estimate is organised
| Code | Description | Qty | Unit | Rate | Total |
|---|---|---|---|---|---|
| PBF4015 | Bath (supply) | 1 | each | 612.15 | 612.15 |
| CJB4000 | 600 mm cupboards and tops, laminate | 1.1 | lm | 1,383.90 | 1,522.29 |
| WTB1915 | Wall tiles (supply) | 7.4 | m² | 65.00 | 481.00 |
| WTB2020 | Wall tiling (labour) | 7.4 | m² | 73.00 | 540.20 |
| PIL2500 | Install vanity basin (labour) | 1 | each | 620.00 | 620.00 |
Figures: Renovation Estimating price library, current rates, ex GST. Interface layout is illustrative.
Flexible construction pricing
Every cost item in our library carries eight pricing levels, from entry level to high-end custom. Changing the level re-prices the estimate, so the effect of a specification decision is visible before it is made.
Complete Bathroom Fitout up to 6 m² — recipe total by pricing level
54 cost items · ex GST| Item | Unit | Level 1 | Level 4 | Level 8 |
|---|---|---|---|---|
| Bath (supply) | each | $198 | $612 | $4,789 |
| Vanity cupboards and top | lm | $585 | $1,384 | $4,126 |
| Wall tiles (supply) | m² | $25 | $65 | $195 |
| Cabinet length | Level 1 | Level 4 | Level 8 |
|---|---|---|---|
| 5 m of cabinets | $14,578 | $41,778 | $156,824 |
| 8 m of cabinets | $20,015 | $55,104 | $200,697 |
| 12 m of cabinets | $25,782 | $69,125 | $247,950 |
Figures: Renovation Estimating price library recipes at current rates, ex GST, rounded to the nearest dollar. Library costs only; a project estimate adds site-specific scope and allowances. Selector layout is illustrative.
Intelligent construction technology
Our AI-assisted processes support the interpretation of construction plans, quantity take-off and documentation review. Measured quantities are drawn back onto the plans as a markup layer, so they can be checked against the original documents.
01
Interprets architectural plans and construction documentation.
02
Assists with identifying and measuring construction quantities.
03
Highlights inconsistencies, missing information and items needing investigation.
04
An estimator verifies every quantity before it is priced.
Technology enhances the process. Professional estimating judgement remains essential.
The takeoff
Measured quantities are drawn back onto the plans as a markup layer, so they can be checked against the original documents.
Figures: measured from the floor plan shown. Wall and opening heights are assumed for this demonstration.
Kitchen takeoff · 1:100
Bench runs, sink, island and cooktop are measured from the plan. Cabinet layout and finishes are illustrative.
Documentation audit & reporting
AI-assisted documentation review flags issues in the information used to prepare the estimate. Each observation is recorded in a structured audit report, so the client can see what was found, what was assumed and what still needs to be confirmed.
Applied to our own price library
3,400
recipe options reviewed
295
potential omissions and corrections flagged
1,272
recipes listed for estimator review
| Ref | Category | Observation | Action |
|---|---|---|---|
| A-01 | Drawing observation | Window W04 is 2,400 wide on the floor plan and 2,100 wide on the elevation. | Confirm with the designer. |
| A-02 | Missing information | Beam size over the new 6.0 m opening is not shown. Engineering not yet issued. | Provisional allowance; confirm on engineering. |
| A-03 | Specification gap | Floor finish to the new family room is not specified. | Priced at the selected level; client to confirm. |
| A-04 | Potential omission | No stormwater connection is shown for the new 32 m² roof area. | Allowance included and flagged. |
| A-05 | Quantity discrepancy | Measured wall-tile area is 7.4 m²; the finishes schedule states 9.0 m². | Estimator to re-measure. |
| A-06 | Clarification | Existing floor level relative to the new slab is not confirmed. | Request survey levels. |
Conceptual example prepared for this publication. Not taken from a client project.
The Renovation Estimating Company